Construction on Bank Street - New Respite Home

December 4, 2008

There was something on the lens when taking these photos so they are not the best quality, but still pretty amazing to see the progress!

       

 

November 14, 2008

     

 

October 30, 2008

     

  October 23, 2008

     

Where we are in the construction process:

Things are moving along nicely and we should have power to the building in about 3 weeks. We could also have a road in as little as 2 weeks!  The house has a full roof now and the ceilings are going up in both the Adult and Children's wings this week.  The stone is almost complete on the back of the house and the siding will be installed soon after.

October 15, 2008

October 8, 2008

 

September 10, 2008